Planning a 2027 Remodel in DFW: What to Do in Which Month
A spring 2027 remodel is mostly decided in December, January and February. Here is the month-by-month plan we would give a Dallas–Fort Worth homeowner today, built around the dates already on the 2027 calendar.
“Start early” is the usual 2027 advice. This plan names the decision for each month and the date that forces it, counted back from demolition day.
For a spring 2027 remodel in DFW, make the decisions in December, January and February, so construction starts with every selection made and delivered.
Selections are the part of the schedule you control. And ask whether your cabinets and vanity are imported: from most countries, the duty is scheduled to rise from 25% to 50% on January 1, 2027.
Month by month, for an April start
This is an example for a bathroom built from April, not a booked start date. For a summer start, slide each row about three months; the right-hand dates don’t move.
December: decide what the project is
Settle the layout first
On our Plano master bath, the tub moved to a new spot. The drains in a North Texas slab home sit under the concrete, so that meant saw-cutting the slab, re-routing the drain, setting rebar and pouring back to the original floor height before any tile. The slab work was priced in the scope before demolition, so it never became a change order.
Decide now whether the sink, tub, toilet, range or a wall moves. Everything after is priced off that answer.
Put a ceiling on the budget
Our remodeling cost calculator gives a planning range from a few quick questions; the in-home visit replaces it with a scope and one price. Our minimum project is $10,000. If several rooms need work, decide now whether 2027 is a one-room year or a whole-home renovation year. Rooms done in separate seasons mean separate rounds of demolition and dust.
The January 1 tariff step
Imported kitchen cabinets and bathroom vanities from most countries, parts included, have carried a 25% Section 232 duty since October 14, 2025; the UK, the EU and Japan have separate rates (C.H. Robinson). It is scheduled to rise to 50% on January 1, 2027. That step was first set for January 1, 2026, and on December 31, 2025 it was pushed back a year, citing “productive negotiations of agreements with multiple countries” (Thompson Hine). So the date is scheduled, and it has moved once already.
This step hits imported cabinet and vanity lines, not tile or labor. Ask where a cabinet line is made before you fall for a door style. Prices were rising anyway: in October 2026, US building materials excluding energy were up 5.8% on the year, and particleboard and fiberboard 13.9% (NAHB, from BLS data).
Two tax credits that are gone
Per the IRS, the 25C Energy Efficient Home Improvement Credit is not allowed for property placed in service after December 31, 2025, and the 25D Residential Clean Energy Credit is not allowed for expenditures made after that date. Older articles that promise them are out of date.
January: the first visit and the 3D design
The first visit is free, takes about an hour and needs no deposit. The 3D design is free too, and you see it before you sign. Each estimate gives one price for the agreed scope. How we work lays out every step after that.
What to have ready before the first visit
- Photos of each room, and close-ups of whatever bothers you.
- Two lists: what has to change, and what stays.
- A few inspiration photos. Three you love beat thirty you like.
- A budget ceiling, and how you’ll pay.
- Your HOA’s architectural rules, if the outside changes.
- Appliance models, for a kitchen. Their spec sheets set the cabinet openings.
- Dates that can’t move: a graduation, a baby, a closing.
Not sure which of these applies to your house? A short conversation settles it faster than any calculator.
February: lock every selection
Tile, tub, fixtures, glass, cabinets, counters, hardware, appliances: each one chosen, priced and ordered. A late selection holds up every step built on top of it.
To get a bathroom finished sooner, have every selection made and delivered before the first day of demolition.
Two 2026 jobs, and what set their calendars
Plano master bath: four weeks on site
Signing to handover took longer, because the homeowners were choosing and buying their own tile, tub, fixtures and glass, and were away for part of it. Their pace set the start date.
Plano again: three changes after signing, each in writing
No change goes ahead until you approve its scope and price in writing. If you already know you want more, put it in the first scope.
Garland whole-house refresh: floors, kitchen and paint, contracted at four to five weeks
The contract set roughly 1,950 square feet of luxury vinyl plank, a refinished kitchen with new quartz, and interior paint at four to five weeks of construction. The homeowners chose the cabinet pulls and supplied the half-bath wallpaper. Owner-supplied items share the February deadline.
March: permits, and the code your city enforces
We pull the permits and coordinate the city inspections. Moving plumbing, gas, circuits or framing generally needs a residential permit; like-for-like cosmetic work generally doesn’t. Statewide, the 2026 National Electrical Code has been the Texas electrical code since September 1, 2026 (TDLR). The building code edition is each city’s call:
So a headline saying Texas adopted the 2024 codes doesn’t settle your house: Dallas still enforces its 2021 codes. In an HOA, file the architectural review request with the permit drawings, not after them.
April onward: the build
A bathroom build is 3 to 4 weeks at our Essential tier, 5 to 7 at Refined and 7 to 8 at Custom, after design, selections and permits. Kitchens and whole homes vary too much by scope for one honest number here.
The Legislature sits January 12 to May 31 (Legislative Reference Library of Texas), so HOA, ADU or property-tax bills may pass while your project is under way. ADU rules stay city by city: the 2025 state ADU bill, SB 673, died in the House (Texas Legislature Online).
Tell us what you are planning. We will walk your house, tell you what is actually possible, and put a real number on it before you commit to anything.
Paying for it in 2027
These carry their dates. None is a DFW quote.
- HELOCs averaged 7.47% nationally on November 18, 2026 (Bankrate, 10 largest banks and thrifts).
- Fannie Mae’s October 2026 forecast puts the 30-year fixed mortgage at 7.5% in every quarter of 2027 (via Florida Realtors).
- In Texas, a home-equity loan plus all other debt secured by your homestead can’t exceed 80% of the home’s fair market value when the loan is made, and the loan can’t close until 12 days after the later of your application or the required notice (Texas Finance Commission).
- A remodel that adds value is taxed on top of the 10% homestead cap, as a new improvement; repairs and ordinary maintenance don’t count. For owners 65 or older or disabled, adding to or enlarging the home can raise the school-tax ceiling (Texas Comptroller).
Four mistakes that push a 2027 start back
Demolition before selections
The room sits open while a tile order ships.
Pricing the layout late
In a slab home, a moved drain is a concrete job.
Assuming one code for DFW
Frisco and Dallas enforce different editions.
Waiting on tariff news to start designing
The 3D design is free and comes before you sign.
If 2027 is a whole-home year
A whole-home remodeling project follows the same order, with more selections to order and more trades to schedule. The April build in the table is sized for a bathroom; a whole home’s build depends on its scope. Tell us your target start date, and we’ll work backward from it with you.
Questions we get
When should I start planning a remodel for spring 2027?
In December or January. Settle the layout and budget, do the first visit and 3D design in January, and order every selection in February, so permit applications go in during March and your side is ready for a spring build.
Is it better to remodel now or wait until later in 2027?
We have seen no forecast of remodeling costs falling in 2027. US building materials excluding energy were up 5.8% year on year in October 2026, and the duty on cabinets and vanities imported from most countries is scheduled to double on January 1, 2027.
Do I need a permit to remodel a kitchen or bathroom in DFW?
Generally yes, once you move plumbing or gas, change electrical circuits or change framing; like-for-like cosmetic work generally doesn’t. Electrical work follows the 2026 National Electrical Code, the Texas electrical code since September 1, 2026. We pull the permits and coordinate the inspections.
Which building code does my DFW city use?
Frisco has enforced the 2024 IRC with amendments since March 1, 2026. Colleyville moved to the 2024 editions on April 1, 2025. Dallas still enforces its 2021 codes. Elsewhere, ask the building department.
Can I still get a federal tax credit for energy upgrades in 2027?
No. Per the IRS, the 25C Energy Efficient Home Improvement Credit is not allowed for property placed in service after December 31, 2025, and the 25D Residential Clean Energy Credit is not allowed for expenditures made after that date.
How long does a bathroom remodel take?
Our bathroom builds run 3 to 4 weeks at the Essential tier, 5 to 7 at Refined and 7 to 8 at Custom. Design, selections and permits come first. On our Plano master bath, the crew’s work took four weeks on site.
December: layout and budget. January: first visit and 3D design. February: selections. March: permit applications. April: a bathroom build can start. Outside dates: January 1 (tariff step, scheduled), January 12 to May 31 (the Legislature), and the 2026 NEC on every electrical permit.
Related from the journal

Tell us your target start date, and we’ll work backward from it.
1-year workmanship warranty · serving 21 communities across Dallas–Fort Worth.
Prefer to talk? (469) 850-7087 · or use the contact page.